Billing migration: go-live holds at March 2 if the discount import fix lands by December 12
- Report
- Week 7 of 16, December 1 to December 5, 2026
- Owner
- Priya Nair, engineering manager
- For
- Steering group: product, finance, engineering
On plan, with one risk that can move the date. Customer and subscription data is migrated to the new billing provider in the sandbox and reconciled. Annual plans with custom discounts still fail to import; the provider promises a fix for December 12.
Status by area
- ScheduleAmber
Renewal testing slips a week while discounted plans fail. Go-live stays March 2 if the fix arrives by December 12.
- BudgetGreen
$186,000 spent of $420,000, 2% under plan for week 7.
- ScopeGreen
No change. Usage-based pricing stays in phase 2, as agreed in week 3.
- PeopleGreen
Both support leads joined testing this week.
Done this week
- Sandbox migration complete: 18,400 customer accounts, reconciled to 0.3% difference in monthly revenue, inside the 0.5% target.
- Checkout tested on 400 test orders across card, invoice and PayPal, no blocking defects.
- Support training agreed: 6 sessions in February, 40 people.
Next week
- Test renewals and upgrades on monthly plans, which import cleanly.
- Get the fix date from the provider in writing.
- Draft the cut-over weekend plan for the steering group on December 15.
Risks and issues
- Issue: discounted annual plans do not import. Impact: 1,150 accounts, $2.1M in annual revenue, cannot renew on the new system. Owner: Tom, payments engineering. Provider fix due December 12.
- Risk: renewal peak overlap. If go-live moves past March 2, it lands in the April renewal peak. Owner: Priya. Mitigation: decision below.
Decision needed
By December 15: approve $9,600 for a contractor to write a one-off import script for discounted annual plans, as a fallback if the provider fix is late. Without it, a missed fix moves go-live to May.
Milestones
- Sandbox migrationDec 5Done
- Billing tests completeJan 23At risk
- Support trainedFeb 20On track
- Go-liveMar 2At risk