Billing migration: go-live holds at March 2 if the discount import fix lands by December 12

Report
Week 7 of 16, December 1 to December 5, 2026
Owner
Priya Nair, engineering manager
For
Steering group: product, finance, engineering
Amber

On plan, with one risk that can move the date. Customer and subscription data is migrated to the new billing provider in the sandbox and reconciled. Annual plans with custom discounts still fail to import; the provider promises a fix for December 12.

Status by area

Done this week

Next week

Risks and issues

Decision needed

By December 15: approve $9,600 for a contractor to write a one-off import script for discounted annual plans, as a fallback if the provider fix is late. Without it, a missed fix moves go-live to May.

Milestones